Sprint Plan: {project_name}

Scrum Master로서 **스프린트 계획** 워크플로우를 실행합니다.

Scrum Master로서 스프린트 계획 워크플로우를 실행합니다.

Workflow Overview#

Goal: Plan sprint iterations with detailed, estimated stories

Phase: 4 - Implementation (Planning)

Agent: Scrum Master

Inputs: PRD or tech-spec, architecture (if Level 2+), team capacity

Output: docs/sprint-plan-{project-name}-{date}.md, .bmad/sprint-status.yaml

Duration: 30-90 minutes (varies by project level)

Required for: All project levels (approach varies by level)


Pre-Flight#

  1. Load context per helpers.md#Combined-Config-Load
  2. Check status per helpers.md#Load-Workflow-Status
  3. Load planning documents:
    • Check for PRD: docs/prd-*.md
    • If no PRD, check for tech-spec: docs/tech-spec-*.md
    • If Level 2+, load architecture: docs/architecture-*.md
  4. Check sprint status per helpers.md#Load-Sprint-Status
    • If exists: Resume or plan next sprint
    • If not: First-time sprint planning
  5. Extract from planning docs:
    • Project level (0-4)
    • Epics (if PRD) or high-level features (if tech-spec)
    • All functional requirements
    • Story estimates (if already present)
  6. Load ZenHub context per helpers.md#Load-ZenHub-Context
    • This automatically loads conventions cache first (per helpers.md#Load-ZenHub-Conventions)
    • Check zh_sub_tasks_enabled for Sub-task support

Sprint Planning Process#

Use TodoWrite to track: Pre-flight → Extract Requirements → Break Into Stories → Estimate Stories → Calculate Capacity → Allocate to Sprints → Define Goals → Generate Plan → Update Status → ZenHub Batch Sync

Approach: Organized, pragmatic, team-focused.


Part 1: Extract and Inventory#

From PRD (Level 2+):

  • Extract all epics (Epic-001, Epic-002, etc.)
  • For each epic, extract associated FRs
  • Note epic priorities (Must/Should/Could Have)
  • Count total epics and FRs

From Tech-Spec (Level 0-1):

  • Extract requirements list (simple features)
  • Note priorities
  • Count total requirements

From Architecture (if exists):

  • Review component structure (guides story breakdown)
  • Note technical dependencies
  • Identify infrastructure stories needed

Create inventory:

Project Inventory:
- Level: {0|1|2|3|4}
- Epics: {count} (if PRD)
- Requirements: {count}
- Architecture: {exists|not needed}
- Estimated Stories: {rough count based on level}

Part 2: Break Epics Into Stories#

For each epic (or feature group):

  1. Identify user stories within the epic

    • Each story should deliver incremental value
    • Stories should be independent where possible
    • Stories should be testable
  2. Apply story template:

    ### STORY-{number}: {Title}
    
    **Epic:** {Epic ID/name}
    **Priority:** {Must Have | Should Have | Could Have}
    
    **User Story:**
    As a {user type}
    I want to {capability}
    So that {benefit}
    
    **Acceptance Criteria:**
    - [ ] Criterion 1
    - [ ] Criterion 2
    - [ ] Criterion 3
    
    **Technical Notes:**
    {Implementation guidance, components involved, dependencies}
    
    **Dependencies:**
    {Other stories or external dependencies}
    
  3. Size appropriately:

    • Level 0: 1 story total
    • Level 1: 1-10 stories
    • Level 2: 5-15 stories
    • Level 3: 12-40 stories
    • Level 4: 40+ stories
  4. Ensure completeness:

    • All FRs are covered by at least one story
    • Stories map back to epics/requirements
    • No orphaned requirements
  5. Sub-task decomposition (if zh_sub_tasks_enabled):

    • For stories estimated at 5+ points, suggest sub-task breakdown
    • Sub-tasks represent discrete implementation units within a story
    • Each sub-task should be completable in 1-4 hours
    • Present sub-task suggestions for user approval:
      STORY-001 (5 pts) suggested sub-tasks:
        - Implement data model and migration
        - Create API endpoint with validation
        - Build frontend component
        - Write unit and integration tests
      
      Add sub-tasks? (y/n/edit)
      
    • Store approved sub-tasks in sprint plan for later ZenHub sync

Typical breakdown patterns:

Authentication Epic →

  • STORY-001: User registration
  • STORY-002: User login
  • STORY-003: Password reset
  • STORY-004: Email verification
  • STORY-005: Profile management

Product Catalog Epic →

  • STORY-006: Product listing page
  • STORY-007: Product search
  • STORY-008: Product detail page
  • STORY-009: Product categories
  • STORY-010: Product images

Infrastructure (if needed) →

  • STORY-000: Set up development environment
  • STORY-INF-001: Database schema
  • STORY-INF-002: CI/CD pipeline
  • STORY-INF-003: Deployment infrastructure

Part 3: Estimate Story Points#

For each story, assign points using Fibonacci scale:

Estimation guidelines:

  • 1 point: Trivial (1-2 hours) - Config change, text update
  • 2 points: Simple (2-4 hours) - Basic CRUD, simple component
  • 3 points: Moderate (4-8 hours) - Complex component, business logic
  • 5 points: Complex (1-2 days) - Feature with multiple components
  • 8 points: Very Complex (2-3 days) - Full feature frontend + backend
  • 13 points: Epic-sized (3-5 days) - BREAK THIS DOWN

Estimation factors:

  • Complexity of business logic
  • Number of components/files to change
  • Dependencies on other stories
  • Testing complexity
  • Unknowns or research needed

Ask user for estimation input (if needed):

"I've estimated STORY-006 (Product listing page) at 8 points (2-3 days). Does this align with your expectations given it includes:

  • API endpoint for products
  • Frontend listing component
  • Pagination
  • Filtering
  • Unit and integration tests

Adjust if your team's velocity differs."

Store estimates:

STORY-001: User registration - 5 points
STORY-002: User login - 3 points
STORY-003: Password reset - 3 points
...

Total Points: {sum} points

Validate:

  • No story >8 points (break down if needed)
  • Point distribution is balanced
  • Infrastructure stories are included

Story Point Correction Table: When sub-tasks are enabled, verify point estimates against sub-task count:

PointsExpected Sub-tasksIf MoreIf Fewer
1-20-2Bump to 3 ptsOK
32-4Bump to 5 ptsOK
53-6Bump to 8 ptsConsider removing sub-tasks
85-10Break into 2 storiesOK
13+ ALWAYS break down Split into 2-3 stories Still split

Part 4: Calculate Team Capacity#

Ask user:

"Let's determine your sprint capacity.

Questions:

  1. How many developers on the team? (default: 1)
  2. Sprint length in weeks? (default: 2 weeks)
  3. Any holidays or PTO during sprint?
  4. Team experience level? (Junior: 4h/day, Mid: 5h/day, Senior: 6h/day productive)"

Calculate capacity:

Team size: {developers}
Sprint length: {weeks} weeks = {days} workdays
Productive hours/day: {hours} (default: 6)
Holidays/PTO: {days} off
Total hours: {developers} × ({days} - {days_off}) × {hours}

Convert to story points:

Velocity (if known from past sprints): {points/sprint}

If no velocity:
- Junior team: 1 point = 4 hours
- Mid team: 1 point = 3 hours
- Senior team: 1 point = 2 hours

Capacity = Total hours ÷ hours per point

Example:

1 senior developer
2-week sprint = 10 workdays
6 productive hours/day
No holidays
Total: 1 × 10 × 6 = 60 hours
Velocity: 60 ÷ 2 = 30 points per sprint

Store capacity:

Sprint Capacity: {points} points
Team Size: {developers}
Sprint Length: {weeks} weeks

Part 5: Allocate Stories to Sprints#

Level 0 (1 story):

  • No sprint allocation needed
  • Just create the single story
  • Proceed directly to /dev-story

Level 1 (1-10 stories):

  • Single sprint
  • Allocate all stories
  • Order by priority and dependency
  • Total points: {sum}

Level 2+ (Multiple sprints):

For each sprint:

  1. Start with Must Have stories
  2. Respect dependencies (don't schedule dependent stories in wrong order)
  3. Fill to capacity (target: 80-90% of capacity for safety)
  4. Group related stories (keep epic stories together when possible)
  5. Leave buffer (10-20% for unknowns and bugs)

Sprint allocation format:

### Sprint 1 (Weeks 1-2) - {points}/{capacity} points

**Goal:** {What this sprint delivers}

**Stories:**
- STORY-001: User registration (5 points) - Must Have
- STORY-002: User login (3 points) - Must Have
- STORY-003: Password reset (3 points) - Should Have
- STORY-000: Development environment setup (2 points) - Infrastructure
- STORY-INF-001: Database schema (5 points) - Infrastructure

**Total:** 18 points / 30 capacity (60% utilization)

**Risks:**
- {Any identified risks for this sprint}

**Dependencies:**
- {External dependencies}

---

### Sprint 2 (Weeks 3-4) - {points}/{capacity} points

**Goal:** {What this sprint delivers}

**Stories:**
...

Validate allocation:

  • All Must Have stories are allocated
  • Dependencies are respected
  • Sprints are balanced (not overloaded)
  • Each sprint has a clear goal
  • Buffer exists for unknowns

Part 6: Define Sprint Goals#

For each sprint, create a clear goal:

Good sprint goals:

  • "Complete user authentication with registration, login, and password reset"
  • "Deliver product catalog with listing, search, and detail views"
  • "Enable checkout flow from cart to order confirmation"

Bad sprint goals:

  • "Do some stuff" (too vague)
  • "Finish everything" (not specific)
  • "STORY-001 through STORY-020" (not user-focused)

SMART goals:

  • Specific: What exactly is being delivered
  • Measurable: Clear success criteria
  • Achievable: Fits within capacity
  • Relevant: Delivers user value
  • Time-bound: Fits within sprint timeframe

Part 7: Create Traceability#

Epic to Story mapping:

## Epic Traceability

| Epic ID | Epic Name | Stories | Total Points | Sprint |
|---------|-----------|---------|--------------|--------|
| Epic-001 | User Authentication | STORY-001, 002, 003, 004, 005 | 21 points | Sprint 1 |
| Epic-002 | Product Catalog | STORY-006, 007, 008, 009, 010 | 28 points | Sprint 1-2 |
| Epic-003 | Shopping Cart | STORY-011, 012, 013 | 15 points | Sprint 2 |
| Epic-004 | Checkout | STORY-014, 015, 016, 017 | 20 points | Sprint 3 |

FR to Story mapping:

## Functional Requirements Coverage

| FR ID | FR Name | Story | Sprint |
|-------|---------|-------|--------|
| FR-001 | User registration | STORY-001 | 1 |
| FR-002 | User login | STORY-002 | 1 |
| FR-003 | Password reset | STORY-003 | 1 |
...

Ensures:

  • All FRs are covered
  • All epics are broken down
  • No requirements are forgotten
  • Clear implementation path

Part 8: Identify Risks and Dependencies#

For the overall plan:

Risks:

  • Technical risks (new technology, integration complexity)
  • Resource risks (team availability, holidays)
  • Dependency risks (external APIs, third-party services)
  • Scope risks (unclear requirements, scope creep)

Format:

## Risks

**High:**
- Integration with payment gateway (Stripe) - mitigation: prototype in Sprint 1
- Database performance at scale - mitigation: load testing in Sprint 2

**Medium:**
- Email delivery reliability - mitigation: use SendGrid, monitor bounces

**Low:**
- Browser compatibility issues - mitigation: test on major browsers

Dependencies:

  • External teams or services
  • Infrastructure provisioning
  • Design assets
  • Third-party API access

Part 9: Generate Sprint Plan Document#

Load sprint plan template (if exists) or use default structure:

# Sprint Plan: {project_name}

**Date:** {date}
**Scrum Master:** {user_name} (Steve)
**Project Level:** {level}
**Total Stories:** {count}
**Total Points:** {sum}
**Planned Sprints:** {count}

---

## Executive Summary

{2-3 sentence overview of the sprint plan}

**Key Metrics:**
- Total Stories: {count}
- Total Points: {sum}
- Sprints: {count}
- Team Capacity: {points} points per sprint
- Target Completion: {date}

---

## Story Inventory

{All stories with estimates, acceptance criteria, dependencies}

---

## Sprint Allocation

{Sprint-by-sprint breakdown from Part 5}

---

## Epic Traceability

{Epic-to-story mapping from Part 7}

---

## Requirements Coverage

{FR-to-story mapping from Part 7}

---

## Risks and Mitigation

{Risks from Part 8}

---

## Dependencies

{Dependencies from Part 8}

---

## Definition of Done

For a story to be considered complete:
- [ ] Code implemented and committed
- [ ] Unit tests written and passing (≥80% coverage)
- [ ] Integration tests passing
- [ ] Code reviewed and approved
- [ ] Documentation updated
- [ ] Deployed to {environment}
- [ ] Acceptance criteria validated

---

## Next Steps

**Immediate:** Begin Sprint 1

Run /create-story to create detailed story documents for Sprint 1 stories, or run /dev-story {STORY-ID} to implement a specific story.

**Sprint cadence:**
- Sprint length: {weeks} weeks
- Sprint planning: Monday Week 1
- Sprint review: Friday Week 2
- Sprint retrospective: Friday Week 2

---

**This plan was created using BMAD Method v6 - Phase 4 (Implementation Planning)**

Save document:

  • Path: {output_folder}/sprint-plan-{project-name}-{date}.md
  • Use Write tool

Part 10: Initialize Sprint Status#

Create or update .bmad/sprint-status.yaml:

version: "6.0.0"
project_name: "{project_name}"
project_level: {level}
current_sprint: 1
sprint_plan_path: "{path to sprint plan}"

# Epic Branch Tracking (populated by Part 11 Step 5)
epic_branches: []
  # - epic_id: "{zh_epic_id}"
  #   epic_name: "{epic_name}"
  #   branch: "epic/EPIC-{number}-{slug}"
  #   created: false       # lazy-created on first story start
  #   pr_url: ""           # epic → main PR URL
  #   pr_status: ""        # open | merged | closed

sprints:
  - sprint_number: 1
    start_date: "{date}"
    end_date: "{date + 2 weeks}"
    capacity_points: {capacity}
    committed_points: {committed}
    completed_points: 0
    status: "not_started"
    goal: "{sprint goal}"
    stories:
      - story_id: "STORY-001"
        title: "{title}"
        points: {points}
        status: "not_started"
        assigned_to: null
        zh_issue_id: ""        # ZenHub issue ID (populated by ZenHub sync)
        zh_issue_number: null  # GitHub issue number
        zh_issue_url: ""       # GitHub issue URL
        branch: ""             # story branch (populated by Part 11 Step 5 or dev-story)
        epic_branch: ""        # parent epic branch
        pr_url: ""             # story → epic PR URL
        pr_status: ""          # open | merged | closed

velocity:
  sprint_1: null  # Will be filled when sprint completes
  sprint_2: null
  rolling_average: null

team:
  size: {developers}
  sprint_length_weeks: {weeks}
  capacity_per_sprint: {points}

Save per helpers.md#Update-Sprint-Status


Display Summary to User#

Show concise summary:

✓ Sprint Plan Created!

Project: {project_name} (Level {level})

Summary:
- Total Stories: {count}
- Total Points: {sum}
- Planned Sprints: {count}
- Team Capacity: {points} points/sprint
- Target Completion: {date}

Sprint 1 Goal: {goal}
Sprint 1 Stories: {count} stories, {points} points

Full plan: {file_path}

ZenHub Sync: (if zh_available)
- Epics created: {count}/{total}
- Stories created: {count}/{total}
- Sprint assignments: {count}

Ready to begin implementation!

Update Workflow Status#

Per helpers.md#Update-Workflow-Status:

  1. Update sprint-planning status to file path
  2. Set current phase to "implementation"
  3. Save status file

Part 11: ZenHub Batch Sync#

Skip this part if zh_available = false.

Step 0: Preview and Confirm

Before creating any ZenHub issues, display a full preview:

=== ZenHub Batch Sync Preview ===

Issues to create:
  Epics: {count}
  Stories: {count}
  Sub-tasks: {count}  (if zh_sub_tasks_enabled)

  [Epic] {epic_1_name}
    [Story] {story_1_title} ({points} pts)
      [Sub-task] {sub_1_title}  (if sub-tasks)
      [Sub-task] {sub_2_title}
    [Story] {story_2_title} ({points} pts)

  [Epic] {epic_2_name}
    [Story] {story_3_title} ({points} pts)
    ...

Sprint Assignment: {sprint_name}
Pipeline: Sprint Backlog (current sprint) / Product Backlog (future)

Total Issues: {total_count}
Total Points: {total_points}

[C]onfirm - Create all issues
[S]kip sub-tasks - Create epics + stories only
[A]bort - Skip ZenHub sync entirely

Wait for user confirmation. If abort, skip Part 11 entirely.

Step 1: Sync Epics

For each epic in the sprint plan:

  1. Generate epic body per helpers.md#Generate-Epic-Body:
    • epic_name, epic_description, stories list, sprint info
  2. Call helpers.md#Sync-Epic-to-ZenHub with:
    • epic_name: Epic title from plan
    • epic_description: Generated body (markdown)
    • sprint_start_date / sprint_end_date: From sprint dates
  3. Collect zh_epic_id for each epic
  4. Log: ✓ Epic synced: [Epic] {name} → #{issue_number}

Step 2: Sync Stories

For each story in the sprint plan:

  1. Generate story body per helpers.md#Generate-Story-Body:
    • story data (user story, AC, technical notes)
  2. Call helpers.md#Sync-Story-to-ZenHub with:
    • story_title: Story title
    • story_body: Generated body (markdown)
    • story_points: Estimated points
    • zh_epic_id: Parent epic's ZenHub ID (from Step 1)
    • sprint_id: zh_active_sprint.id (current sprint) or zh_next_sprint.id (future sprint)
    • pipeline_id: zh_pipelines["Sprint Backlog"] (current sprint) or zh_pipelines["Product Backlog"] (future sprints)
  3. Collect zh_story_id, issue number, URL for each story
  4. Log: ✓ Story synced: [Story] {title} → #{issue_number}

Step 3: Sync Dependencies

  1. Build dependency_map from story dependencies identified in Part 8
  2. Call helpers.md#Sync-Story-Dependencies-to-ZenHub with dependency_map
  3. Log each dependency created

Step 4: Store Cross-References

  1. For each synced epic/story, call helpers.md#Store-ZenHub-Cross-Reference:
    • Update sprint-status.yaml with zh_issue_id, zh_issue_number, zh_issue_url
    • Update sprint plan document with ZenHub cross-reference table:
## ZenHub Cross-Reference

| Local ID | ZenHub # | Type | URL |
|----------|----------|------|-----|
| Epic-001 | #{number} | Epic | {url} |
| STORY-001 | #{number} | Story | {url} |
| STORY-002 | #{number} | Story | {url} |

Step 5: Pre-compute Branch Names

For each epic and story, compute branch names using helpers.md#Resolve-Branch-Names:

  1. For each epic:

    • Compute: epic/EPIC-{zh_issue_number}-{slug}
    • Store in sprint-status.yaml epic_branches section:
      epic_branches:
        - epic_id: "{zh_epic_id}"
          epic_name: "{epic_name}"
          branch: "epic/EPIC-{number}-{slug}"
          created: false
      
    • Note: Branch is NOT created here — lazy creation on first story start (dev-story Part 3)
  2. For each story:

    • Compute: story/STORY-{id}-{slug}
    • Store in sprint-status.yaml story entry:
      branch: "story/STORY-{id}-{slug}"
      epic_branch: "epic/EPIC-{number}-{slug}"
      
  3. Log pre-computed branch names:

    Branch Names Pre-computed:
    epic/EPIC-025-coui-flutter-maintenance
      ├── story/STORY-008-dcm-warning-zero
      └── story/STORY-009-widgetbook-update
    

Step 6: Sync Sub-tasks (if zh_sub_tasks_enabled and user confirmed sub-tasks in Step 0)

For each story that has approved sub-tasks:

  1. For each sub-task: a. Generate sub-task body per helpers.md#Generate-Sub-task-Body b. Call helpers.md#Sync-Sub-task-to-ZenHub:
    • sub_task_title, sub_task_body
    • zh_story_id (parent story from Step 2) c. Collect zh_sub_task_id, issue number
  2. Update sprint-status.yaml story entry with sub_tasks array:
    sub_tasks:
      - id: "sub-task-001"
        title: "{sub_task_title}"
        status: "not-started"
        zh_issue_id: "{zh_sub_task_id}"
        zh_issue_number: {issue_number}
        zh_issue_url: "{url}"
        zh_pipeline: "Sprint Backlog"
    
  3. Update metrics: total_sub_tasks
  4. Log: ✓ Sub-task synced: #{issue_number} (parent: #{story_number})

Display ZenHub sync results in summary:

ZenHub Sync Results:
- Epics created: {count}/{total}
- Stories created: {count}/{total}
- Sub-tasks created: {count}/{total}  (if sub-tasks enabled)
- Sprint assignments: {count}
- Dependencies synced: {count}
- Branch names pre-computed: {count} epics, {count} stories

Recommend Next Steps#

Level 0:

✓ Sprint plan complete (1 story)

Next: Implement the story
Run /dev-story STORY-001 to begin implementation

Level 1-2:

✓ Sprint plan complete ({sprints} sprint{s})

Next: Begin Sprint 1
Options:
1. /create-story STORY-001 - Create detailed story document
2. /dev-story STORY-001 - Start implementing immediately
3. /sprint-status - Check current sprint status

Recommended: Start with /dev-story for first story

Level 3-4:

✓ Sprint plan complete ({sprints} sprints)

Implementation roadmap ready:
✓ Sprint 1: {goal}
✓ Sprint 2: {goal}
✓ Sprint 3: {goal}
...

Next: Begin Sprint 1
Run /dev-story STORY-001 to start first story

Or run /create-story STORY-XXX to generate detailed story docs

Helper References#

  • Load config: helpers.md#Combined-Config-Load
  • Load status: helpers.md#Load-Workflow-Status
  • Load sprint status: helpers.md#Load-Sprint-Status
  • Save document: helpers.md#Save-Output-Document
  • Update sprint status: helpers.md#Update-Sprint-Status
  • Update workflow status: helpers.md#Update-Workflow-Status
  • Recommend next: helpers.md#Determine-Next-Workflow
  • ZenHub context: helpers.md#Load-ZenHub-Context
  • ZenHub conventions: helpers.md#Load-ZenHub-Conventions
  • Sync epic: helpers.md#Sync-Epic-to-ZenHub
  • Sync story: helpers.md#Sync-Story-to-ZenHub
  • Sync sub-task: helpers.md#Sync-Sub-task-to-ZenHub
  • Sync deps: helpers.md#Sync-Story-Dependencies-to-ZenHub
  • Store xref: helpers.md#Store-ZenHub-Cross-Reference
  • Generate epic body: helpers.md#Generate-Epic-Body
  • Generate story body: helpers.md#Generate-Story-Body
  • Generate sub-task body: helpers.md#Generate-Sub-task-Body
  • Resolve branches: helpers.md#Resolve-Branch-Names

Story Point Calibration#

Use these examples to calibrate estimates:

1 point (1-2 hours):

  • Update configuration value
  • Change text/copy
  • Add simple validation
  • Fix typo in code

2 points (2-4 hours):

  • Create basic CRUD endpoint
  • Simple React component (no state)
  • Add database index
  • Write unit tests for existing code

3 points (4-8 hours):

  • Complex React component with state
  • Business logic function
  • Integration test suite
  • API endpoint with validation

5 points (1-2 days):

  • Feature with frontend + backend
  • Database migration with data transformation
  • Complex business logic with edge cases
  • Full test coverage for feature

8 points (2-3 days):

  • Complete user flow (e.g., registration)
  • Multiple related components
  • Complex state management
  • Integration with external service

13 points (3-5 days):

  • TOO BIG - BREAK IT DOWN
  • This is an epic, not a story

Tips for Effective Sprint Planning#

Right-size stories:

  • Target: 2-5 points per story
  • Avoid: 1-point stories (too granular) and 13-point stories (too large)
  • Ideal sprint: Mix of 2, 3, 5, and 8-point stories

Balance sprints:

  • Don't front-load all hard stories
  • Mix Must/Should/Could priorities
  • Leave buffer for unknowns (10-20%)

Respect dependencies:

  • Infrastructure before features
  • Foundation before extensions
  • Backend before frontend (usually)

Keep user value visible:

  • Each sprint should deliver something usable
  • Demo-able progress at sprint end
  • Incremental value delivery

Notes for LLMs#

  • Maintain approach (organized, pragmatic, team-focused)

  • Use TodoWrite to track 10 sprint planning parts

  • Break stories systematically - don't skip any FRs

  • Apply sizing guidelines strictly (no stories >8 points)

  • Calculate realistic capacity based on team size and experience

  • Create traceability tables to ensure coverage

  • Reference helpers.md for all common operations

  • Initialize sprint status YAML for tracking

  • Hand off to Developer when ready for implementation

  • After local plan is complete (Part 10), sync to ZenHub (Part 11) if zh_available

  • Always show preview (Step 0) and wait for confirmation before creating ZenHub issues

  • Use createGitHubIssue (not createZenhubIssue) per workspace convention

  • Use Generate Body helpers for consistent issue formatting (Epic/Story/Sub-task bodies)

  • Set issue types: Epic for epics, Feature for stories

  • Assign stories to active sprint (Sprint Backlog) or future sprints (Product Backlog)

  • Store ZenHub cross-references in sprint-status.yaml for downstream workflows

  • Sub-tasks are opt-in: only suggest for 5+ point stories when zh_sub_tasks_enabled = true

  • Sub-task sync (Step 6) happens after stories, as each sub-task needs parent zh_story_id

  • If ZenHub sync fails partially, log what succeeded and continue

  • After ZenHub sync, pre-compute branch names (Part 11 Step 5) using helpers.md#Resolve-Branch-Names

  • Store branch names in sprint-status.yaml for dev-story to use (epic_branches + story branch/epic_branch fields)

  • Branches are NOT created during sprint planning — only names are pre-computed for consistency

Remember: Good sprint planning = smooth implementation. Poor planning = chaos, delays, and frustration. Take time to break stories down properly and estimate accurately.